Need drainage repair to get moisture out from under your home or near the foundation? Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been fixing drainage problems to create dry crawl spaces and dry foundations in San Francisco for over 24 years. You will see our trucks and equipment working in San Francisco neighborhoods like the Marina, Pacific Heights, Nob Hill, Western Addition, Haight, Castro, Noe Valley, Twin Peaks and so on.
Here’s the kind of detailed estimate you can rely on, to correct foundation problems and perform structural work, including even zero lot line jobs that require our expertise:
This is an estimate based on unsigned and undated plans provided by contractor. The scope of work includes drilling, installing concrete and steel in pier hole. The price includes all labor and material to complete the work as per the itemized scope of work below.
Scope of Work
Mobilization and Layout
• After existing building has been demolished by others mobilize to jobsite with portable drilling rigs along with other necessary equipment to complete job (See notes below).
• Layout to be completed by others per plans and specifications.
• Daily Cleanup
• Final Cleanup
Piers
• Drill three (3) 18” diameter x 17 ft depth maximum and two (2) 18” diameter x 14 ft depth maximum pier holes with portable drill rig. See drilling conditions and exclusions. Final depths to be determined by soils engineer..
• Install cage per plans and place concrete in hole per plans.
• Includes sono tube as required
• Off haul pier spoils
Slab
• Install approximately 425 sq. ft of 4 inches of light weight concrete over plywood prepared by others per plans. #4 reinforcement @ 18 inches e.w. No waterproofing included.
Qualifications and Clarifications
• Job is bid as package.
• Includes two mobilizations only.
• Prices are subject to adequate supply of wood, steel, rock, concrete, and asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Survey of property lines must be done by licensed surveyor. Survey points must be provided
• Price is preliminary subject to final plans for construction
Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Any additional work due to utilities including buried pipes or irrigation pipes unless noted.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Additional cost as a result of unknown obstructions
• Replacement of damaged landscaping, driveway or fence.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Any work related to landscaping, fences or gates except as outlined
• Survey of property lines or layout
• Landscaping or irrigation
• Excludes electrical and plumbing
• Any earth shoring not included
• Any drainage work
• Embedment into concrete including brackets except J bolts
• Permeable concrete