All posts by admin

Foundation Sinking, Cracking or Settling?? Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been repairing foundation cracks, doing excavation, and drilling work in Berkeley for over 24 years. You will see our trucks and equipment working on homes in Berkeley, the Berkeley Hills, and Kensington neighborhoods.

Call us for a prompt detailed estimate like the one below to correct foundation problems, fix drainage issues, perform structural work, and repair driveways and walls in the Berkeley area:

This is an estimate for replacing a failing wood retaining wall and fence. To prepare this estimate certain assumptions were utilized using standard construction practices and design details. Final price is subject to receipt and review of plans completed by a licensed engineer. An allowance has been provided for plans. Cost of permit is additional. The scope of work includes demo of the existing fence and wall, drilling pier holes, installing concrete in piers with steel I beams, lagging, drainage behind the wall and a redwood fence. Our price includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work

Mobilization and Layout
• Coordinate the preparation of plans with engineer (See Engineering allowance) for permit purposes
• Pull building permit as required (cost of permit is additional)
• Mobilize to jobsite with necessary equipment.
• Grub vegetation as required to install new wall
• Daily Cleanup
• Final Cleanup

Demo and Cut Bench
• Demo existing retaining wall, fence and off haul debris from site.
• Cut bench as necessary to install new wall and drainage per plans and specifications.
• Off haul dirt spoils from site

Piers

• Drill twenty four (24) 16” diameter x 6 ft deep holes with drilling equipment. See hard rock drilling conditions. Final depth to be determined by engineer.
• Install twenty four (24) steel I beams (w8x15) x 6 ft deep in pier holes with concrete (minimum 2500 PSI) per plans and specifications. Coat I beams with two part epoxy for protection.
• Off haul pier spoils from site.

Retaining Wall
• Install 3 X 12 pressure treated lumber approximately 136 linear ft x a maximum of 3 ft high per plans and specifications. Treat cut ends with copper green.
• Allow ¼ inch gap between lagging for drainage

Drainage
• Install approximately 12 cubic yds of drain rock 1 ft wide behind retaining wall 1 ft from top of grade.
• Install approximately 136 linear ft of perforated SDR 35 pipe wrapped in filter fabric and exit at end of wall.

Compaction
• Install a native soil cap on top of drain rock approximately 1 ft in depth and compact.

Fence
• Install a redwood fence (construction grade) on top of retaining wall a maximum of 5 ft high approximately 136 linear ft.
• Fence is to be constructed using 4×4 posts with 2×4 framing and 1×8 fencing material
• Include approximately 35 additional ft of fence on the side with 4×4 posts approximately 3 ft deep
Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only
• Prices are subject to adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules
• Price includes allowance for engineer and plans. Contractor to engage engineer and coordinate all design requirements with engineer to obtain plans for permit. It will require contract to be executed with owner.
• Final price is contingent on receipt of plans and confirmation of assumptions used for estimate.
Exclusions
• Cost of plans permits, bonds, testing and inspections.
• Increased cost of drilling or excavation due to hard rock, underground water or caving soils. (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes.) (Hard rock excavation is defined as material that cannot be excavated with a conventional backhoe or excavator bucket.)
• Any work on utilities including buried pipes or irrigation pipes.
• Replacement of damaged landscaping.
• Embedments into concrete other than foundation bolts.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Structural or Earth Shoring
• Additional drainage not specifically outlined in this proposal.
• Importation of backfill material except as noted.
• Damage to trees or cost of arborist
• Cost of surveyor if required

 

Foundation Sinking, Cracking or Settling?? Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been repairing foundation cracks, doing excavation, and drilling work in Berkeley for over 24 years. You will see our trucks and equipment working on homes in Berkeley, the Berkeley Hills, and Kensington neighborhoods.

Call us for a prompt detailed estimate like the one below to correct foundation problems, fix drainage issues, perform structural work, and repair driveways and walls in the Berkeley area:

This estimate is based on drawings provided by engineer. The scope of work includes, drilling and installing concrete reinforced piers, footings, and concrete retaining walls with concrete stairs. It includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work

Mobilization and Layout
• Mobilize to jobsite with track equipment and other necessary equipment to complete job.
• General Contractor to provide layout
• Daily Cleanup
• Final Cleanup

Piers
• Excavate bench for installation of wall and piers.
• Drill nineteen (19) 18” diameter x 14 ft. deep piers per plans and specifications S1, A/S1, B/S1 and C/S1. Final depths to be determined by soils engineer. See hard rock drilling conditions.
• Drill seven (7) 18” diameter x 19 ft. deep piers per plans and specifications S1, A/S1, B/S1 and C/S1. Final depths to be determined by soils engineer. See hard rock drilling conditions.
• Install nineteen (19) 18” diameter x 14 ft. deep concrete reinforced piers per plans and specifications S1, A/S1, B/S1 and C/S1.
• Install seven (7) 18” diameter x 19 ft. deep concrete reinforced piers per plans and specifications S1, A/S1, B/S1 and C/S1.
• Pier spoils to be removed by others. No off haul from site.

Concrete Footings
• Excavate for footings per plans and specifications S1, A/S1, B/S1 and C/S1.
• Install approximately 157 linear ft concrete reinforced footings per plans and specifications S1, A/S1, B/S1 and C/S1.
Concrete Retaining Walls
• Install 8 inch thick shotcrete concrete reinforced retaining walls a maximum of 3.5 ft tall per plans and specifications S1, A/S1, B/S1 and C/S1.
• Finish walls with smooth steel troweled finish.
• Approximate square footage 625.
• Include approximately 625 sq. ft of Miradrain on retaining walls.
Concrete Stairs
• Install concrete reinforced stairs per plans and specifications S1 and 1/S1. Approximately 14 stairs with 17 risers.
• Install concrete reinforced stairs to replace existing stairs up to street. Approximately 9 stairs and landing.
Drainage
• Include approximately 160 linear ft of 4” perforated pipe SDR 35 surrounded in drain rock behind retaining wall wrapped in filter fabric per plans and specifications S1, A/S1, B/S1 and C/S1.
• Final exit for Perforated pipe to be handled by others.

Concrete Parking Pad
• Install approximately 230 sq. ft of concrete reinforced parking pad on grade with broom finish. Parking pad is to be reinforced with #4 rebar 18” o.c.
Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only
• Prices are subject to adequate supply of wood, steel, rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• All spoils to be handled by others. No off haul of any spoils.
• All backfill and compaction to be handled by others. No backfill or compaction.
• All concrete demo to be handled by others

Exclusions

• Cost of plans, permits, bonds, testing and inspections.
• Increased cost of drilling or excavation due to hard rock, underground water or caving soils. (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes.) (Hard rock excavation is defined as material that cannot be excavated with a conventional backhoe or excavator bucket.)
• Any work on utilities including buried pipes or irrigation pipes.
• Replacement of damaged landscaping, driveway or fence.
• Off haul of any dirt spoils (all spoils to remain on site for backfill or off hauled by others.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Removal of any trees
• Additional drainage not specifically outlined in this proposal.
• Electrical or Plumbing
• Backfill or Compaction of any soils not outlined in this proposal.
• Importation of backfill material except as noted.
• Pavers or stone on walkway or walls.

 

Foundation Sinking, Cracking or Settling?? Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been repairing foundation cracks, doing excavation, and drilling work in Berkeley for over 24 years. You will see our trucks and equipment working on homes in Berkeley, the Berkeley Hills, and Kensington neighborhoods.

Call us for a prompt detailed estimate like the one below to correct foundation problems, fix drainage issues, perform structural work, and repair driveways and walls in the Berkeley area:

This estimate is based on structural drawings for the installation of new foundation additions at the first and second floors of the existing house.

Our price includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work
• Mobilize to jobsite.
• Install conveyor belt from the second floor area up to the street level for off-hauling of excavation and pier spoils. Remove conveyor belt after excavations and piers spoils removal are completed.
• Excavate for new kitchen foundation (Excavation includes the cutting into the existing bank for the installation of new retaining wall footings, piers and drainage pocket). Off-haul all spoils from site.
• Drill and install (4) 24” diameter x 29 ft. deep reinforced concrete piers. Off-haul spoils from site.
• Install Paraseal waterproofing membrane and Miradrain 6000 drainage panels over waterproofing. Terminate drainage panels into a perforated 4” SDR 35 pipe at perimeter base. Backfill behind foundation with a 1ft. thick drain rock pocket wrapped in filter fabric, as per detail 6/S5. (Alternate; use class 2 permeable without filter fabric). Daylight drain line at the outside corner of the new kitchen/dinning area. Outlet/runoff by others.
• Drill and install approx. 16 reinforced epoxy dowels to attach new to old foundation as per plans.
• Install new reinforced concrete grade beams, footings and retaining walls as per plans. (Walls to be single-side formed or shotcreted.)
• Clean up site and remove all construction debris from site.

Unit prices
• For increased pier depths-Add cost per linear ft. No deducts.

Alternate 1
• Drill and install (4) 24” diameter x 29 ft. deep reinforced concrete piers as per plans. No off-haul of drilling spoils is included in this price.

Alternate 2
• The approval from the structural engineer to use of edge drain along the bottom of the retaining walls avoiding cutting in to the hill for a rock pocket and the use of the shotcrete method for the installation of the retaining wall will generate a credit to be deducted from the original total price up above.

Notes
• Layout and elevations to be performed by general contractor.
• Because of the existing headroom, rebar cages for the piers are required to be spliced in (3) sections for the installation in to the drilled pier holes, proper overlaps will be provided.

 

Exclusions
• Cost of plans, permit, bonds, testing and inspections.
• Soft demolition.
• Foundation demolition.
• Earth shoring.
• Structural shoring.
• Underpinning.
• Increased costs of drilling or excavation due to hard rock, underground water or caving. (Hard rock drilling is defined as a penetration rate slower than 1ft. in 5 minutes. Hard rock excavation is defined as material that requires the use of pneumatic jackhammers to excavate.)
• Any work on utilities including buried pipes.
• Off-haul of materials unacceptable at dump.

 

 

Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been doing foundation, excavation, and drilling work in San Francisco for over 24 years. You will see our trucks and equipment working in San Francisco neighborhoods like the Marina, Pacific Heights, Nob Hill, Western Addition, Haight, Castro, Noe Valley, Twin Peaks and so on.

Here’s the kind of detailed estimate you can rely on, to correct foundation problems and perform structural work, including even zero lot line jobs that require our expertise:

This estimate is based on architectural drawings, civil drawings and structural drawings. The proposal is for the installation of a new reinforced concrete foundation per structural drawings as well as earth shoring system per structural drawings.

Scope of Work
Mobilization and Supervision
• Mobilize to jobsite. Demobilize.
• Supervision.
• Perform weekly cleanup.
Grubbing and clearing work area
• Grub and clear work site area of all vegetation (except trees and stumps) plus remove the cleared materials and strippings from site.

Existing house structure structural shoring
• Install combination of post, driven pipe pile and cribbing towers with temporary beams to support the existing house structure at elevation 140 as per plans. Installation of cribbing towers to be performed in conjunction with house foundation demolition operations and mass excavation for cribbing tower installation. Removal of cribbing towers once house is re-attached to new foundations (by others) is included.
House & Garage Foundation Demolition for New foundation Installation
• Demolish and remove from site the existing house foundation including the existing house chimney, concrete walkways, concrete stairs, existing garage foundation, existing garage structure & wooden deck, plus scrape existing driveway AC. Includes demolition of all visible concrete foundations for the installation of the new foundations shown on structural drawings. All soft demolition to be provided by GC. See requested broken-down prices provided on sheet one.
• Off-haul all demolished debris from site.

Tieback & shotcrete shoring installation
• Drill and install (116) at 60 kips (design capacity) 1” diameter double corrosion-protected 150 ksi diameter tieback bars in 6” diameter drilled shafts extending into soil as per plans (Includes bonded and un-bonded lengths). Off-haul drilling spoils from site.
Note: tiebacks are included at different embedment depths and with bonded and un-bonded lengths accordingly as shown on detail 1/S3.0. For the house, tiebacks at elevation 118’ = 39 ft. total embedment, @ elevation 124’ = 44 ft. total embedment & @ elevation 130’ = 49 ft. total embedment & @ elevation 136 (where applies) = 54 ft. total embedment. The same bonded un-bonded equation applies for the new car elevator area east, north and south sides @ elevations; 139’ 145’ 151’ & 157. An allowance for the installation of a total of 5107 total linear ft. of bonded and un-bonded lengths is included in this estimate.
• Install in sequence a 3” thick layer of reinforced concrete shotcrete in 5 ft. lifts for earth shoring purposes and interlock with a rebar whaler grid system installing a standard nut and 6”x6” washer to lock the temporary earth retention system as excavation proceeds downward.

Mass house foundation & car elevator excavation
• Excavate to new house foundation & sub-grades per elevations shown on drawings. No import is included in this estimate. All native spoils are assumed acceptable to be used for re-compaction.
• Off-haul excess soils from site.

Pier installation
• Drill and install (61) 18” diameter x 20 ft. deep maximum reinforced concrete piers. An allowance of 1220 linear ft. of reinforced concrete piers is included.
• Off-haul excess soils from site.

Backfill and re-compaction operations
• As job progresses and coordinating the installation of the new house retaining wall plus site plan driveway wall sequence with General Contractor, re-use approx. 450 cubic yards of native soil for backfilling and re-compaction behind the new retaining walls mentioned above to create the new auto court area. Includes cutting a maximum of 4 ft. wide x 12” stepped base footings into the native slopes as standard procedure prior to commence re-compaction operations. All excavated spoils generated from “stepped benching to be re-compacted as well.
• Off-haul excess soils from site. See notes below.

Notes:
1. An estimated approx. 1950 cubic yards of dirt will be extracted from the original existing grades to achieve the new slab sub-grades, excavation for the new house & car elevator foundation. At the same time a rough calculation for the re-compaction requirements is approx. 450 cubic yards of the native soil, an excess of approx. 1500 cubic yards of dirt to be off-hauled from site.
2. The excavation price provided includes the off-haul of 1500 cubic yards from site and includes excavation, loading, transportation and dump fees. No deducts

House S2.1, S2.2 & 2.3 & new carport S2.4 foundation + site walls S2.6 concrete work
• For the new garage foundation level per sheet S2.4, install new 5” thick reinforced concrete slab over a new 24” thick x 5 ft. wide perimeter footing foundation per 1/S3.0 retaining/concrete walls.
• For the new third level, floor foundation level, and as per sheet S2.3, install new 5” thick reinforced concrete slab over a new 24” thick x 5 ft. wide perimeter footing foundation per 1/S3.0 retaining/concrete walls. Omit installation of mud/storage room at this level as shown on structural sheet S2.3.
• For the new level two, floor second level, and as per sheet S2.2, continue east side walls up to elevation 140’ plus install new mud/storage room 18” thick mass footing and perimeter walls.
• For the new main house level and as per sheet S2.1, install shown 10” thick elevated slab at new mud/storage room + storage foundation.
• Includes the installation of a new site walls per layout and height retained on sheet S2.6.
• Clean up construction debris from site.
Alternate #1 Erosion Control
• Per indications on C-500
Alternate #2 Utility lines
• A multiline trench approx. 120 ft. long x 36” deep x 18” wide backfilled with 18” of fill sand and 18” of native soil.
• A single service line trench approx. 120 linear ft. long x of 24” wide x 18” deep. Backfill trench with 8” of sand and re-compacted native soil to cap the rest of the trench.

Alternate #3 Earth work area winterization
• Install 6 mil plastic with sand bags over it for temporary winterization as needed.
Alternate #4 Concrete Driveway (optional)
• Install a new 5” thick structural concrete driveway slab on grade for driveway (2905 sq. ft. allowance) area.
Alternate #5 Stump removal
• Remove native sumps from site (up to 36” in diameter)
Notes
• Existing structures protection, adjacent structures protection, elevations, layout and secured batter boards as well as elevation story poles to be provided and confirmed by General Contractor prior to concrete installation.
• Trees to be removed (by others) are assumed to be removed prior to mobilization and brake-ground day.
• Waterproofing and drainage membranes are to be provided and installed by others (please see limited backfill and re-compaction scope above).
• Elevations, provide of elevation story pole, layout providing, checking & confirmation of and secured batter boards to be provided by General Contractor performing the remainder of the project.
• Native soils are assumed acceptable to be used for backfill and re-compaction where needed. Import of engineered fill or any other type of import for re-compaction materials (if needed) is not included in this estimate.
• All walls are assumed Shotcrete installation approved for cost savings. If board formed walls are selected see additional cost and add it to preliminary pricing at each alternate.
• New auto court sub-grades re-compaction operations assumed benching into exiting grades by a standard 12” deep x maximum 4 ft. wide benches. No additional excavations or re-compaction of un-acceptable existing sub-grades is assumed at this point. In an event the project soils engineer requires to over excavate existing grades and backfill and re-compact the driveway area with native soils down to acceptable bearing native materials to receive the new re-compaction operations included in our preliminary proposal additional cost will apply.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Itemized provided pricing is shown as reference and per request of the GC. Itemized prices are not self-supporting.
• Includes one mobilization only.
• Prices are subject to adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Progress payments every two weeks. No retention.
Exclusions
• Cost of plans, shop drawings, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Tree removal, stump removal
• Site drainage.
• Erosion control and winterization.
• Demolition or removal of buried or unknown concrete or other structures (e.g. deep footings, massive footings, buried concrete walls etc.) beyond reasonable (12” below grades x thicknesses above grades) assumed existence of at the time this proposal was being put together.
• Mock ups.
• Driveway resurface, driveway related walls (not outlined on structural drawings), or new auto court installation, concrete stairs, walkways, or any other concrete work not outlined on the current structural drawings or included in our scope of work.
• Metal I-beams/metal work, welding related or any related not mentioned above.
• Precast concrete, integral color slabs or other concrete work not outlined in our scope of work.
• Street sidewalk, street entry driveway, street-curb concrete work or driveway asphalt work.
• Tanks (provided and installed by plumbing contractor), house downspouts or any other plumbing work not related to scope of work outlined above.
• Drainage, waterproofing membranes, water stop plus perimeter edge drains/aqua drains for all new concrete walls.
• Plumbing work, zurn drains, plumbing lines, sump/ejector pit installation or any other work not mentioned in our quote.
• Provide or install of shrink/leveling grout.
• Soil injection/Soil grouting.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Additional cost due to utility obstructions including any additional work on underground utilities or buried pipes.
• Supply of embedments for concrete work other than foundation “J” bolts.

 

Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been doing foundation, excavation, and drilling work in San Francisco for over 24 years. You will see our trucks and equipment working in San Francisco neighborhoods like the Marina, Pacific Heights, Nob Hill, Western Addition, Haight, Castro, Noe Valley, Twin Peaks and so on.

Here’s the kind of detailed estimate you can rely on, to correct foundation problems and perform structural work, including even zero lot line jobs that require our expertise:

This estimate is based on plans by structural engineer. The bid consists of installing a new reinforced concrete section of house foundation on piers plus installing isolated pier/caps with tiebacks as shown on drawings. 

Our price includes all labor and material to complete the job as per the itemized “Scope of Work” below.

Scope of Work
Wall Foundation Reinforcement
• Mobilize to jobsite. Demobilize.
• Supervision. Perform weekly cleanup.
• Temporarily support the existing corner of the building where the existing foundation needs to be replaced on shoring towers for the replacement of the existing foundation, saw-cut and demolish the portion of the existing concrete foundation as shown on drawings. Remove demolished foundation debris from site.
• Drill and install (10) 18” diameter x 18 ft. deep reinforced concrete piers with (4) #7 vertical reinforcement and #3 ties @ 10” on center. Stockpile drilling spoils on site.
Note: Due to soil conditions outlined on the soils report for this project and the unknown pier final depths (to be dictated by the project soils engineer at the time of drilling, we have included a pier drilling allowance for the installation of the new reinforced concrete piers and it consists of (5) 8hr. drilling days and is included in this estimate.
• Core drill (7) 8” diameter holes thru the existing concrete wall for the installation of the tiebacks.
• Drill and install (7) 15 kip capacity (lock-off load) x 30’ deep total depth 1” diameter double corrosion-protected tiebacks in 6” diameter drilled shafts (Includes bonded and un-bonded lengths). Stockpile drilling spoils on site.
Note: Due to the site soil conditions outlined on the soils report for this project, we have included a tieback drilling allowance for the installation of (7) tiebacks and it consists of (3.5) 8hr. drilling days and is included in this estimate.
• Excavate for and install (7) reinforced concrete haunches/pier caps at each of the (7) pier location as shown on drawings. All generated spoils to be stockpiled on site
• Excavate for and install a new reinforced concrete grade beam over (3) new piers as per plans. Includes the installation of (3) new HDG-CBSQ 66’s as per plans.
• Proof test and lock-off tiebacks as shown on drawings (22.5 k).
• Clean-up and remove related construction debris from site.

Alternate #1-Piers Casing Installation Cost
• This additional cost is for installing a maximum of (3) 20” diameter (4 ft. sections) continuous metal casing at each pier location due to unstable native soils outlined on soils report. The additional cost is per pier (if required).
Alternate #2-Piers Casing Removal Cost
• This additional cost is for the removal of the metal casing previously installed (if needed) as concrete is being placed per indications on drawings. The additional cost is per pier (if required).
Alternate #3-Tiebacks Casing Installation and Removal Cost
• This additional cost provided is for the installation and removal of the metal casing at each tieback location for a maximum of 10 ft. (if needed). The additional cost also includes the removal of the 8” diameter metal casing section as grout is being placed per indications on drawings. The additional cost is per tieback at each location (if required).

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Standard drilling conditions.
• Progress payments every two weeks.
Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, tree roots, caving conditions, underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes.)
• Tree work, tree service or any additional work generated by existing trees of tree roots.
• Demolition hard or soft other than necessary for temporary structural shoring installation.
• Any work on utilities including buried pipes.
• Soil grouting, soil injection or permeation.
• Framing work or carpentry work or replacement of existing framing not mentioned in our scope of work.
• Structural/earth shoring, house re-leveling (unless mentioned in our scope of work).
• Removal of generated spoils from site.
• Waterproofing and drainage.
• Erosion control.
• Winterization.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Architectural concrete or type of special concrete finish product.
• Chimney underpinning or work related to it.

Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been doing foundation, excavation, and drilling work in San Francisco for over 24 years. You will see our trucks and equipment working in San Francisco neighborhoods like the Marina, Pacific Heights, Nob Hill, Western Addition, Haight, Castro, Noe Valley, Twin Peaks and so on.

Here’s the kind of detailed estimate you can rely on, to correct foundation problems and perform structural work, including even zero lot line jobs that require our expertise:

This revised estimate is based on revised plans. The bid consists of installing a new reinforced concrete section of house foundation on helical piers plus installing isolated helical pier/caps with helical tiebacks as per revised drawings.

Our price includes all labor and material to complete the job as per the itemized “Scope of Work” below.

Scope of Work
Wall Foundation Reinforcement
• Mobilize to jobsite. Demobilize.
• Supervision. Perform weekly cleanup.
• Temporarily support the existing corner of the building where the existing foundation needs to be replaced on shoring towers for the replacement of the existing foundation, saw-cut and demolish the portion of the existing concrete foundation as shown on drawings. Remove demolished foundation debris from site.
• For the (2) isolated vertical piers below the new concrete foundation, install a total of (2) 17 ft. deep Foundation-SupportWorks HP-287 helical piers. Helical piers include (1) 7 ft. 8”–10” galvanized lead helix plate configuration with 3/8-inch thick grade 50 steel standard helix plate configuration plus (2) 5 ft. galvanized extensions and (1) galvanized HP288NCBA-G bracket assembly each. Test measuring installation torqueing rates as per plans. Other type of field testing (pull testing or compression testing) is not included. See additional cost provided below.
• For the (8) vertical piers (against the foundation) where the vertical pier interacts with the horizontal helical tieback, at each location install a total of (8) 17 ft. deep Foundation-SupportWorks HP-287 helical piers. Helical piers include (1) 7 ft. 8”–10” galvanized lead helix plate configuration with 3/8-inch thick grade 50 steel standard helix plate configuration plus (2) 5 ft. galvanized extensions and (1) galvanized FS288BLRA-G bracket assembly at each vertical helical pier/helical tieback location. For the tieback interaction at each of the (8) vertical helical pier locations, install a total of (8) 35 ft. long Foundation-SupportWorks HA-150 helical tieback. Helical tiebacks include (1) 7 ft. 10”–12”-14” galvanized lead helix plate configuration with 3/8-inch thick grade 50 steel standard helix plate configuration plus (4) 7 ft. galvanized extensions each. Attach bracket assembly to house foundation per vertical/lateral bracket assembly configuration at (8) locations via epoxy doweled bolts encapsulated in concrete at each location.
• Excavate for and install (7) reinforced concrete haunches/helical pier caps at each of the (7) pier location as shown on drawings. All generated spoils to be spread on site (rear yard per client’s instructions).
• Excavate for and install a new reinforced concrete grade beam over (3) new piers as per plans. Includes the installation of (3) new HDG-CBSQ 66’s as per plans.
• Clean-up and remove construction debris from site.

Notes:
• Additional footage for helical pier depths
• Pull testing or compression testing of helical piers is not included in the main estimate (base bid) and the amount of the helical piers that can be tested will depend on requirements by the project’s engineer. If pull testing or compression testing are required, testing will be performed on a time and material basis.
• For re-calibration of the testing jack (If required by engineer).
Testing Note: Installation will be made using torque conversion charts as an equivalent to pull test operations. The conversion charts produce installation torque conversion ratings equal to achieved final torque capacities. Proposed Helical pier is based on final installation torque of 34,000 ft-lb = 1200 psi (conversion charts attached) capacity.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Standard drilling conditions.
• Progress payments every two weeks.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, tree roots, caving conditions, underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes.)
• Tree work, tree service or any additional work generated by existing trees of tree roots.
• Increased cost of helical installation due to rubble, boulders, fill or any unknown underground obstruction.
• Demolition hard or soft other than necessary for temporary structural shoring installation.
• Any work on utilities including buried pipes.
• Soil grouting, soil injection or permeation.
• Framing work or carpentry work or replacement of existing framing not mentioned in our scope of work.
• Structural/earth shoring, house re-leveling (unless mentioned in our scope of work).
• Removal of generated spoils from site.
• Waterproofing and drainage.
• Erosion control.
• Winterization.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Architectural concrete or type of special concrete finish product.
• Chimney underpinning or work related to it.

Call 415-457-5658 for a prompt, reliable estimate from our experienced estimator. RWR has been doing foundation, excavation, and drilling work in San Francisco for over 24 years. You will see our trucks and equipment working in San Francisco neighborhoods like the Marina, Pacific Heights, Nob Hill, Western Addition, Haight, Castro, Noe Valley, Twin Peaks and so on.

Here’s the kind of detailed estimate you can rely on, to correct foundation problems and perform structural work, including even zero lot line jobs that require our expertise:

This is an estimate based on unsigned and undated plans provided by contractor. The scope of work includes drilling, installing concrete and steel in pier hole. The price includes all labor and material to complete the work as per the itemized scope of work below.

Scope of Work

Mobilization and Layout
• After existing building has been demolished by others mobilize to jobsite with portable drilling rigs along with other necessary equipment to complete job (See notes below).
• Layout to be completed by others per plans and specifications.
• Daily Cleanup
• Final Cleanup

Piers
• Drill three (3) 18” diameter x 17 ft depth maximum and two (2) 18” diameter x 14 ft depth maximum pier holes with portable drill rig. See drilling conditions and exclusions. Final depths to be determined by soils engineer..
• Install cage per plans and place concrete in hole per plans.
• Includes sono tube as required
• Off haul pier spoils

Slab
• Install approximately 425 sq. ft of 4 inches of light weight concrete over plywood prepared by others per plans. #4 reinforcement @ 18 inches e.w. No waterproofing included.

Qualifications and Clarifications
• Job is bid as package.
• Includes two mobilizations only.
• Prices are subject to adequate supply of wood, steel, rock, concrete, and asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Survey of property lines must be done by licensed surveyor. Survey points must be provided
• Price is preliminary subject to final plans for construction
Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Any additional work due to utilities including buried pipes or irrigation pipes unless noted.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Additional cost as a result of unknown obstructions
• Replacement of damaged landscaping, driveway or fence.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Any work related to landscaping, fences or gates except as outlined
• Survey of property lines or layout
• Landscaping or irrigation
• Excludes electrical and plumbing
• Any earth shoring not included
• Any drainage work
• Embedment into concrete including brackets except J bolts
• Permeable concrete

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed.  RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

Demo, Excavation, Drilling, Concrete Piers,
Concrete Haunches, Concrete Foundation Repair,
Concrete Slab and Concrete Retaining Walls

This estimate is based on structural drawings and Architectural drawings. The scope of work includes demo of concrete, excavation for new retaining walls, haunches and foundation reinforcement, drilling, concrete piers, concrete haunches, concrete footing attachments, new concrete grade beams, new retaining walls and drainage. The price includes all labor and material to complete the work as per the itemized scope of work below.

Scope of Work

Mobilization and Layout
• Mobilize to jobsite with track drilling rigs, portable drilling rigs and Bobcat along with other necessary equipment to complete job (See notes below).
• Layout to be completed by General Contractor per plans and specifications
• All soft demo to be completed by General Contractor. See Notes.
• Daily Cleanup
• Final Cleanup

Demo Concrete
• Demo existing footings as indicated on plans and specifications.
• Off haul debris from site

Piers
• Drill forty nine (49) 18” diameter x 10 ft maximum as shown on plans and specifications S2.0 and S3.0 with track drilling rig where applicable and portable drilling rig where track cannot reach. See drilling conditions and exclusions. Final depths to be determined by soils engineer.
• Install forty nine (49) steel cages and place concrete in holes per plans and specifications S2.0 and S3.l.
• Off haul pier spoils from site.
Note: A drilling allowance of 13 days for portable rigs is being provided. It is anticipated drilling will encounter hard rock.
Excavation
• Excavate per plans and specifications for new retaining walls, haunches and grade beams.
• Where appropriate off haul all dirt spoils not being used for re-installation and compaction.

Concrete Footing Additions
• Install approximately 275 ft of concrete footing addition to existing foundation per plans and specifications S2.0 and 2/S3.0.
• Dowel into existing foundation per plans and specifications using Simpson epoxy or approved equivalent.
• Add a maximum of twenty (20) concrete footing additions (3/S3.0) on opposite side from addition described above centered on holdowns per plans and specifications S2.0 and 3/S3.0..

Concrete Haunches
• Excavate for new concrete haunches where required (32) per plans and specifications S2.0 and 3/S3.0.
• Install new concrete reinforced haunches at each pier called for in plans and specifications S2.0 and 3/S3.0.
• Dowell and epoxy into existing footing per plans and specifications S2.0 and 3/S3.0.
• Off haul spoils from site

Concrete Grade Beams
• Excavate for new concrete grade beams where required per plans and specifications S2.0 and 10/S3.0.
• Install approximately 30 ft of new concrete grade beams 2 ft x 1 ft per plans and specifications S2.0 and 10/S3.0.

Retaining Walls
• Excavate for new concrete foundation per plans and specification for new retaining walls S2.0 and S3.0.
• Install new concrete reinforced footings for new retaining walls per plans and specifications S2.0 and S3.0.
• Install new 12 inch concrete reinforced retaining walls a maximum of 8 ft high per plans and specifications S2.0.
• Includes Miradrain for retaining walls per plans and specifications S2.0 and S3.0.
Drainage
• Install approximately 55 ft of 4 inch perforated SDR 35 pipe behind new retaining walls in a rock pocket (approximately 1 ft x 1 ft) at bottom of new retaining wall per plans and specifications S2.0 and S3.0. Miradrain mentioned above is to terminate at bottom of wall into rock pocket.
• Final exit of drainage per civil plans for connection to drainage system (See Drainage Alternative).

Slab
• Install approximately 200 sq ft of new 6 inch thick concrete structural slab with w #4 @ 16” e.w. on 2 in of sand, over a 10 mil vapor barrier and 4 in of crushed rock with thickened edge.

 

Note: This job site requires extensive work under the house with new piers and new additions to existing footings. It is anticipated that much of the existing floor will have to be removed and replaced to allow this installation. This estimate assumes General Contractor will undertake and complete work necessary to allow this installation as RWR determines.

 

Alternative #1

Drainage

• Install approximately 125 ft of SDR 35 4 inch tight line (SDR 35) capturing drainage from retaining walls and down spouts to drain exit (bio-swale) on side of house per civil drawings C1.0.
• Install 4 down spouts to tight 4 inch line
• Install 22 ft NDS trench drain at driveway per plans and specifications C1.0 and connect to 4 inch tight exit line.
• Install two Catch Basins per plans and specifications C1.0.
• Install approximately 25 linear ft of 6 inch tight SDR 35 pipe from the upper catch basin to the lower catch basin.
• Install a 50 ft x 5 ft Bio Swale for drainage exit per plans and specifications C1.0 and C3.0.
o Includes 1 ft x 1.5 ft rock pocket with 6 inch SDR 35 perforated pipe approximately 50 linear ft. per plans and specifications
o Includes imported sandy loam material per plans and specifications 50 ft x 5 ft x 1 ft. installed over a 30 mil vapor barrier.
o Install 2 in deep ½ inch drain rock on surface per plans and specifications C1.0 and C3.0
Alternative #2

Concrete Stairs Behind House

• Install new concrete reinforced stairs behind house per plans and specifications C1.0.
• Price includes standard stair footings with no stem walls. Approximately 24 treads.
Alternative #3

Catchment Wall Behind House

• Install approximately 35 linear ft for a new 4 ft high Catchment Wall behind house per plans and specifications C1.0 and C3.0.
• Bench and cut for installation of new wall approximately 35 linear ft x 4 ft tall.
• Drill seven (7) piers approximate 7 ft deep per plans and specifications.
• Place into seven (7) holes concrete with 6×6 PT wood posts per plans and specifications
• Install 3×12 PT lagging per plans and specifications C1.0 and C3.0. Leave ¼ gap between boards for drainage.
• Install drain rock behind wall a maximum of 3 ft high capped with 1 ft of native soil per plans and specifications.
Qualifications and Clarifications
• Job is bid as package.
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of wood, steel, rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• RWR is not responsible for survey lines. Survey of property lines must be done by licensed surveyor.
• Soils report from Nersi Hemati dated August 26, 2009 was provided. Report was referenced for this estimate but scope of work is limited to that as shown above.
• Progress payments every two weeks.
• General Contractor to provide elevations and confirm layout

 

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Any additional work due to utilities including buried pipes or irrigation pipes unless noted.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes). See notes on drilling allowance.
• Replacement of damaged landscaping, driveway or fence.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Any work related to landscaping, fences or gates except as outlined
• Soft demo
• Structural or Earth shoring
• Embedment of any bracket or holdown into concrete other than standard foundation bolts
• Survey of property lines
• Landscaping or irrigation
• Excludes electrical and plumbing including UFER.
• Carpentry except as needed for installation of concrete
• Demo of concrete in excess of 8 inches.
• Exclude stone on slabs, stone veneer on retaining walls.
• Steel posts or structural steel
• Asphalt Concrete

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on structural drawings and architectural plans. The bid is for the installation of a new reinforced concrete house foundation and retaining walls as per plans.

Scope of Work
HOUSE
• Mobilize to jobsite. Demobilize.
• Supervision.
• Install safety barricades as needed.
• Perform weekly cleanup.

Grubbing and Clearing + Excavation
• Grub and clear the lot of brush as necessary for the installation of the new house foundation. Off haul debris from site.
• Mass house excavation to slab sub-grade levels as per architectural plans elevations and structural plans information. Off-haul all excavation spoils from site.
• Excavate for new perimeter footings, grade beams and concrete walls as per plans. Off-haul excavation spoils from site. (Wall excavation will be cut 1” behind back of wall.)

Drill and Install Piers
• Drill and install (57) 18” diameter x 15’ deep reinforced concrete piers as per plans. Off-haul all drilling spoils from site.

Waterproofing + Drainage
• Install Miradrain 6000 drainage panels against outboard cuts at perimeter foundations as per architectural plans and terminate into a 4” diameter SDR 35 perforated pipe at perimeter base in a 1ft. tall x 1ft. thick gravel pocket. (Rock pocket consists of a 4” SDR 35 perforated drain line wrapped in filter fabric surrounded by ¾-crushed gravel).
• Terminate drainage lines at two specific points, one at the corner of A & 5 grid lines and the other one at the front stairs. (Outlet to street location by others).
• Excavate and install all other perimeter perforated foundation drainage lines (Other than mentioned above) as per the drainage site plan page WA1.2.
• Excavate and install approx. (9) new 4” diameter downspouts as per layout on page WA1.2.
• Install approx. 387 linear ft of SDR35 tite line to collect all of the perimeter downspouts at the perimeter of the new house foundation and terminate at two specific points, one at the corner of A & 5 grid lines and the other one at the front stairs. (Outlet to street location by others).

Install Foundation and slabs
• Install all perimeter and interior reinforced concrete grade beams, tie beams, retaining walls for the house structure as per sheets S-2, S-3 from structural plans
• Install the exterior retaining walls as per sheet WA3.2 layout and elevations and structural details on page S-3.
• At new interior garage, laundry room and work shop install a new 5” thick reinforced concrete slab approx. 1180 square ft. with # 5 rebar @ 16” on center each way over 2” of fill sand, 6 mil moisture barrier and 4”of ¾ crushed gravel. Slab to have a smooth troweled finish.
• At new upper exterior terraces, install a new 5” thick reinforced concrete slab approx. 652 square ft. with # 5 rebar @ 16” on center each way over 2” of fill sand, 6 mil moisture barrier and 4”of ¾ crushed gravel. Slab to have a light-broomed finish.
• Clean up RWR related debris from site.

Notes
• Layout and elevations must be provided by general contractor performing the remainder of the project.
Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Sump pump box or any work related to it.
• Any work on utilities including buried pipes.
• Earth shoring.
• Exterior main entrance concrete stairs.
• Driveway, driveway retaining walls and all related to driveway work.
• Supply of embedments other than foundation bolts.
• Any concrete work not mentioned above.
• Masonry/Block walls (Only Concrete Footings for masonry walls are included).

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is being made for piers, rebar and concrete. The bid is based on plans provided. The bid is for drilling and installation of concrete reinforced piers only. The price includes labor and materials to complete the job as per the itemized scope of work listed below.

Scope of Work

Mobilize
Mobilize to jobsite
Layout to be provided by general contractor

Piers
• Drill for twenty five (25) 18” diameter piers. Maximum depth of 8 feet deep per plans and specifications S1.1 and S2.4.
• Install twenty five (25) 18” concrete reinforced piers a maximum of 8 ft deep. Include transfer bars, rebar and concrete. Final depths to be determined by soils engineer. Additional price per ft is $65.00.
• All Spoils to remain on site.
Note. See hard rock drilling exclusion.
Exclusions
• Cost of plans, permits, bonds, inspections and testing.
• Layout
• Any work on utilities including buried pipes.
• Any Excavation
• Increased cost of drilling or excavation due to hard rock, underground water or caving soils. (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes.) (Hard rock excavation is defined as material that cannot be excavated with a conventional backhoe or excavator bucket.)
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Damage or replacement of landscaping.
• No off haul of spoils
• No Drainage