All posts by admin

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on structural drawings. The work includes drilling, installation of a grade beam, drainage and seismic retrofitting. Our price includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work

Mobilization and Layout
• Mobilize to jobsite
• Daily Cleanup
• Final Cleanup

Excavation
• Excavate for new grade beam per plans and specifications D-1 and S5.
• Excavate for seven (7) haunches per plans and specifications.
• Remove concrete from existing grade beam tying deck footing and existing foundation. All existing rebar to remain intact.
• Off haul all dirt spoils and concrete debris from site.

Piers
• Drill seven (7) 18” diameter x 11ft. deep piers per plans and specifications Section C (D-1) and S-5. Final depths to be determined by soils engineer. See Hard Rock Drilling Exclusion.
• Install seven (7) 18” diameter x 11ft deep concrete reinforced piers per plans and specifications Section C (D-1) and S-5. Additional cost per foot installed is equal to $110. NO Deduct.
• Off haul all pier spoils from site.

 

Foundation
• Install concrete reinforced grade beams 24”x 24” per plans and specifications Section C (D-1).
• Repair stucco using Detail 3 (D-1) per plans and specifications.
• Install downspout through grade beam using section F (D-1) per plans and specifications.
• Install seven (7) haunches per plans and specifications (Revised haunch detail).

Drainage
• Install approximately 60ft of solid SDR 35 pipe behind wall and connect to tight line per plans and specifications S-6. Connect to existing D.L. junction box. Note: No other drainage detail provided.
• Include down spout extension (maximum 3).

Seismic Retrofit
• Per plans and specifications S-7 add new 2×6 suds with PHD5-SDS3 brackets as needed for shear wall elevation.
• Add additional foundation bolts as needed using 5/8 threaded rod embedded minimum 7” into existing foundation and 32” o.c. spacing per plans and specifications S-7 (maximum of 50 new bolts).
• Install rough opening door framing with 6” x 12” header. (Door excluded).
• Per plans and specifications S-7 install new shear walls under house on south wall wrapping around on east and west wall as shown on plans.
Alternative #1
• Remove and replace existing small Retaining Wall.
• All contained soil to remain. Include additional spoils from new excavations if applicable.
• Maximum height of new wall not to exceed 24”.
• Piers to be 4ft o.c. using p.t. 4×4 in concrete a maximum of 3ft deep.
• Lagging to be p.t. 2×12.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased cost of drilling or excavation due to hard rock, underground water or caving soils. (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes.) (Hard rock excavation is defined as material that cannot be excavated with a conventional backhoe or excavator bucket.)
• Demolition of any concrete footings greater than 18” deep or any concrete slabs or asphalt greater than 4” thick.
• Cost for any carpentry/woodwork except as outlined in this estimate.
• Any work on utilities including buried pipes or irrigation pipes.
• Replacement of damaged landscaping.
• Embedments into new concrete other than foundation bolts.
• Off-haul of materials unacceptable at dump.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Additional drainage not specifically outlined in this proposal.
• Compaction of any soils not outlined in this proposal.
• Importation of backfill material.
• Electrical or Plumbing
• New access door for crawlspace.

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on architectural drawingsand structural drawings. This bid is for the selective hard demolition, excavation and installation of a new house reinforced concrete foundation as per plans.

Our price includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work
Foundation Work
Excavation
• Excavate for the installation of the new house foundation as per plans. Off-haul excavated spoils from site.
Note: excavation for the new basement slab sub-grades is estimated to be to a maximum of 6 (six) inches below the bottom of the existing slab for new slab under layers (gravel and sand). No mass excavation has been calculated for this project.
Demolition
• Perform existing slab and selective house foundation demolition for the installation of the new basement foundation as per plans. Off-haul demolition debris from site.
• Includes demolition of two existing brick chimneys plus off-hauling debris from site.
Demolition exclusions: Permits, retention, hazardous materials abatement, utility safe-offs, grading and backfilling.
Structural Shoring and House Lifting
• Install combination of post, driven pipe pile and crib towers with temporary beams to support main floor of house. Remove shoring system after house is re-supported on new perimeter and interior foundations (by others).
Shoring exclusions: Soft demolition or any shoring preparation other than removal of existing concrete slab (see cost provided above) for the installation of shoring towers (all preparation work to be provided by general contractor except as noted above).
New Concrete Foundation Installation per S2.1
• Mobilize to jobsite. Demobilize.
• Supervision.
• Perform weekly cleanup.
• For the new house foundation, install new concrete foundation as per structural details on S3.1 and layout on sheet S2.1.
• Install new 4” thick reinforced concrete slabs on grade over 2” of fill sand, 10 mil vapor barrier and 4” of ¾” crushed gravel for the new basement and garage per note 3 on sheets S2.1 and S2.2.
• Clean up RWR related debris and form materials from site.

Retaining Walls Waterproofing and Drainage + Backfill and re-compaction
• Behind the new retaining walls and as indicated on structural drawings, install Paraseal waterproofing membrane and Miradrain 6000 drainage panels over waterproofing. Terminate drainage panels into a perforated 4” SDR 35 pipe at perimeter base. Backfill behind foundation with a 1 ft. thick drain rock pocket wrapped in filter fabric, extending up to one foot below grade as per plans. (as an alternate use class 2 permeable without filter fabric). Outlet drainage lines via a buried 4” diameter SDR 35 tite line and connect to the existing drainage system.
• Backfill the upper one ft. with native soil in compacted.
Additional Work 10-5-2010

Deck Foundation
• Excavate and install foundation for new deck per plans and specifications S2.2, GS3.1 and 4/S3.3.
• Include nine (9) – 2.5 ft x 2.5 ft pad square at depth of 1.5 ft
• Include two (2) – 2.5 ft x 2.5 ft pad square at depth of 2 ft
• Include a grade beam 1 ft x 1.5 ft along perimeter of new deck.

 

Site Retaining Wall
• Install site retaining wall on outside of house per plans S2.1, A/S2.1 and A2.2.
• Demo 456 sq. ft of slab, entrance to existing house and brick stairs and wall per AB2.1
• Excavate back from house approximately 1 ft down (as shown on A4.4) to establish new rough grade. Store spoils on site for future backfill and compaction. No off haul. Excavated area limited to equal area of demo noted above.
• Excavate for new footing of new retaining wall per S2.1 and A/S2.1
• Install new 8 inch thick retaining wall per S2.1 and A2.2 a maximum of 5 ft tall. a maximum of 25 linear ft. Does not include concrete stairs.
• Install Paraseal waterproofing with Miradrain and drainage with 4 in perforated SDR 35 and drain rock per plans.
• Backfill with spoils on site.

Drainage
• Drainage has been estimated using drain plans as shown on D1.0 Drainage Plan, Landscape plans L-1, and Architectural A2.1 and A2.2. It should be noted this additional drainage is limited to items noted in this scope.
• Install 185 ft of tight 4 in SDR 35 pipe for drainage to capture Area drains and downspouts.
• Install ten (10) downspout connectors to tight drain pipe.
• Install five (5) area drains (V1) and connect to tight pipe.
• Install a 16 ft trench drain at garage entrance with traffic grate and connect to tight pipe.
• Install three (3) dissipaters 2 ft x 2 ft x 4 ft. and direct solid 4 inch tight pipe to dissipaters.
• Install two (2) Drywell’s 20 ft long x 2 ft wide x 4 ft deep as shown on D1.0 and detail 3/D1.0. Connect 4 inch pipe as shown on D1.0.

 

Notes:
• Elevations and layout to be provided by General Contractor or surveyor (hired by others) performing the remainder of the project.
• All existing utility lines, heating ducts, electrical wiring, etc. must be removed from the underside of the basement level joists, (by others) prior to the installation of the shoring towers and the commencing of the demolition.
• All soft demolition to be provided by General Contractor.
• Due to temporary shoring installation under the existing house structure and lifting of the structure operations, installation/removal of shoring may result in cracked walls, cracked floors, uneven floors finishes as well as other cosmetic damages. RWR is not including repair of same in this estimate and will not be responsible for such items.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Progress payments every two weeks.
• Itemized prices are for reference purposes only and are not self supporting.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Driveway demolition or any other type of demolition not mentioned in our scope of work.
• Additional cost due to utility obstructions including any additional work on utilities or buried pipes.
• Rat proofing.
• Landscaping work or any additional retaining walls, walkways, patios, tie steps or other concrete work not mentioned in our scope of work.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Architectural concrete or type of special concrete finish product.
• Supply of embedments other than foundation bolts.
• Any work on Cabana foundation

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on architectural drawings and structural drawings by Dave Olnes. The bid consists of installing a reinforced concrete foundation for a new parking structure plus other walls as per plans.

Scope of Work
New Parking Structure
• Mobilize to jobsite. Demobilize.
• Supervision. Perform weekly cleanup.
• Grub work site area of all small vegetation and remove the cleared materials and strippings from site. Includes removal of existing trees & visible stumps.
• Perform all hard demolition as shown on drawings and as necessary for the installation of the new parking structure. Off-haul demolition debris from site.
• Cut hill side for the installation of the new parking foundations. Vertical cuts estimated to be within 1” of back of new walls for allowance of drainage membranes. Off-haul excavated spoils from site. Shotcrete installation method is assumed to be approved for this project.
• Install upper reinforced concrete wall as per detail B on drawings.
• Install new parking structure walls, footings, front walls and footings, concrete walkway, landing, stairs (6/R) and parking area slab. All as per S1. Includes demolition of entry curb + replacement of it.
• Back-fill top 1 ft. behind wall with compacted native soils.
• Clean up site and remove all construction debris and excess soils.

Earth shoring at North/West side
• Install a combination of I-beams and lagging along the north/west side of the new parking structure to support the vertical cut along the mentioned side for the installation of the new garage wall. This is a preliminary price and engineering or drawings are not included.

Add-on for earth Shoring Engineering Drawings
• Engineering approximate cost is provided below and it is based on similar jobs where shoring engineer must review, revise and incorporate shoring with designed foundation.
Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Elevations and layout to be provided by General Contractor performing the remainder of the project.
• Standard RWR drilling conditions.

Note: This bid assumes RWR will be performing services as a Sub-contractor to a General Contractor. Bid assumes contract will utilize standard RWR contractual provisions. RWR reserves the right to accept or reject General Contractor’s contractual provisions.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Demolition of existing concrete footings in excess of 1 ft. thick slabs over 4” thick or any other buried/hidden condition unforeseen by the assumption of normal standards installation procedures.
• Any work on utilities including buried pipes.
• Existing house underpinning or structural shoring.
• Waterproofing membranes (Paraseal) on walls other than new parking area walls.
• Earth shoring other than along north/west side.
• Erosion control
• Winterization.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Architectural concrete or type of special concrete finish product.
• Surveying and Layout.

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on information provided via fax to RWR Construction Inc. The bid is providing an allowance for a total of 24 hours of portable drilling operations plus the installation of (6) helical piers as per plans.

Our price includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work

Helical pier installation

  • Mobilize to jobsite
  • After all existing structures/obstruction and excavations are performed by GC (or by others), RWR to install a total of (6)/10 ft. deep maximum Foundation-SupportWorks HP-287 helical piers. Each helical piers includes (1) 5 ft. double blade (10”-12”) galvanized lead plus (1) 5 ft. galvanized extensions and (1) galvanized bracket assembly as per plans. Field testing (pull testing or compression testing) is not included.

                                                                                                                                              

Helical Pier Notes:

  • Elevations, layout and checking and confirmation of secured batter boards to be provided by General Contractor performing the remainder of the project.
  • Structural shoring, underpinning and earth shoring are not included.
  • Additional footage for helical pier depths
  • Pull testing or compression testing of helical piers is not included in the main estimate (base bid) and the amount of the helical piers that can be tested will depend on requirements by the project’s engineer. If pull testing or compression testing are required, testing will be performed on a time and material basis.

Testing Note: Installation will be made using torque conversion charts as an equivalent to pull test operations. The conversion charts produce installation torque conversion ratings equal to achieved final torque capacities. Proposed Helical pier is based on 22,000 lb. design capacity.

  • For re-calibration of the testing jack (If required by engineer)

Drilling Allowance

  • Mobilization to site.
  • Perform portable drilling work for (3) days (a total of 24 hours included) for drilling (10) 18” diameter x 14 ft. deep maximum with portable drilling equipment.

 

 

Note: This bid assumes RWR will be performing services as a Sub-contractor to a General Contractor. Bid assumes contract will utilize standard RWR contractual provisions. RWR reserves the right to accept or reject General Contractor’s contractual provisions.

 

Qualifications and Clarifications

  • Job is bid as package unless agreement to otherwise
  • Includes one mobilization only.
  • Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
  • Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
  • Progress payments every two weeks.

 

 

Exclusions

  • Cost of plans, permits, bonds, testing and inspections.
  • Any additional work as a result of utilities including buried pipes or irrigation pipes unless noted.
  • Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). Hard rock drilling is defined as a penetration rate slower than 1 ft in five minutes.
  • House (soft) or existing structures demolition or removal of related debris from site.
  • Metal I-beams/metal work or any related not mentioned above.
  • Provide or install of shrink/leveling grout.
  • Additional work related to soil placement at the new landscaping tiered walls (by others).
  • Landscaping concrete, concrete curbs, walls or any additional concrete work not outlined in our proposal.
  • Increased cost of helical installation due to rubble, boulders, fill or any unknown underground obstruction (soils report not available for this project).
  • Additional work related to new parking area, pavers, grading or any work not related to the scope of work mentioned above.
  • Any work on utilities, including buried pipes.
  • Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
  • Architectural concrete, color concrete or any type of special concrete finish product.
  • Additional cost due to utility obstructions including any additional work on underground utilities or buried pipes.
  • Supply of embedments other than foundation “J” bolts.

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on structural plans prepared by Structural Engineer. The bid is for the installation of drilled cast-in-place reinforced concrete piers to stabilize the downhill side of the house as per plans.

Our price includes all labor and material to complete the job as per the itemized Scope of Work below.

Scope of Work
• Mobilize to site.
• Install a temporary chute for spoils off-hauling.
• Demolish and remove from site an existing wooden and concrete pathway as per plans. Remove debris from site.
• Drill and install (7) 18” diameter x 14 ft. deep maximum reinforced concrete piers along downhill side of house and to the northern side of the house foundation as per plans. Sequential installation is required. Off-haul spoils from site.
• Excavate for and install (4) 2 ft. wide x 4.5 ft. long x 1.5 ft. deep and (3) 2ft. wide x 3 ft. long x 1.5 ft. deep reinforced concrete pier caps under existing foundation that are connected to the top of the piers as per plans.
• Repair (4) existing foundation cracks with Simpson epoxy ETI-GV-22 injection as per manufacturers recommendations prior to exterior foundation work.
• Temporarily shore the northern house entry to replace the existing inadequate isolated support with a new reinforced concrete grade beam as per detail 6/S1. Includes a new section of framing cripple wall to tie to new upper structure as per plans.
• Excavate and install approx. 43 linear ft. of reinforced concrete grade beam along the exterior of the existing house foundation and a new walkway perimeter 6” thick concrete stem wall as per plans. Includes approx. (38) reinforced epoxy dowels to tie new to existing foundation and weep holes thru new foundation for water seepage as per plans.
• Backfill walkway area with ¾ crushed rock as per detail 3/S1 to cover a minimum of 4” over new underpinning haunches.
• Install drainage lines as per plans and a new drainage dissipator a maximum of 2 ft. wide x 3.5 ft. long x 2 ft. deep (detail not provided).
• Clean up site and remove RWR construction debris from site.

Notes
• Homeowner’s permission to park RWR’s drilling power pack at the exiting garage approach/entry for the duration of the drilling procedures is necessary.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Progress payments every two weeks.

Unit Prices
• Additional footage for drilled and installed piers
Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, underground water or caving soils. (Hard rock drilling is defined as a penetration rate slower than 1ft. in 5 minutes). (Hard rock excavation is defined as material that requires the use of a pneumatic or hydraulic breaker to excavate).
• Any work on utilities including buried pipes.
• Removal of spoils from site not mentioned above.
• Structural/Earth shoring.
• Repair to landscaping or irrigation.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

This estimate is based on architectural drawings and structural drawings. The bid is for the installation of a new reinforced concrete foundation as per plans plus house sub-drainage work except CONC-1 and CONC-2 slabs.

Scope of Work
House Foundation per S-2.0 & S2.1
• Mobilize to jobsite + Supervision.
• After garage structural shoring is installed (by others), demolish and remove from site existing garage concrete foundation plus existing hardscape elements (see earth shoring additional cost provided below) specifically for the installation of the new reinforced concrete work as per current drawings including drainage rock pockets behind the new garage wall (see alternate for garage board formed walls + alternate for garage shotcrete installation). Off haul demolition debris from site. All soft demolition to be performed by others.
• Excavate for and install new reinforced concrete grade beams, footings, CMU walls and rough concrete stairs per layout and structural details on sheet S-2.0 & S-2.1. Off-haul related spoils from site.
• Includes the installation of Paraseal waterproofing membranes and Miradrain 6000 drainage membranes for all new foundation sub-drainage systems as called on structural drawings for the garage structure and the CMU walls. Outlet to one side of the new garage.
• Clean-up site and remove RWR related construction debris from site
Base bid Broken-down prices provided for illustrative purposes.
• Supervision & Mobilization
• Hard demo & Of-haul
• Excavations & Off-haul
• Concrete foundations & CMU Walls
• WP & Drainage + Backfill and re-compaction
Add-on cost/Earth Shoring
• Preliminary cost for earth shoring installation using metal I-beams & wood lagging along the north and east sides of the existing garage structure. Engineering not included.

Notes:
• Elevations and secured batter boards to be provided by General Contractor performing the remainder of the project.
• Native soils are assumed acceptable to be used for backfill and re-compaction where needed. Import for re-compaction materials (if needed) is not included in this estimate.
• Drainage and waterproofing membranes are based on Paraseal and Miradrain 6000
• CONC-1 & CONC-2 is not included. No architectural concrete is included.
Note: This bid assumes RWR will be performing services as a Sub-contractor to a General Contractor. Bid assumes contract will utilize standard RWR contractual provisions. RWR reserves the right to accept or reject General Contractor’s contractual provisions.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Progress payments every two weeks.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Any additional work as a result of utilities including buried pipes or irrigation pipes unless noted.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). Hard rock drilling is defined as a penetration rate slower than 1 ft. in five minutes.
• Metal I-beams/metal work or any related not mentioned above.
• Provide or install of shrink/leveling grout.
• Earth/Structural shoring (see additional cost provided).
• House drainage work (other than foundation sub-drainage work).
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• CONC-1 & CONC-2 slabs/topping slabs/architectural finishes.
• Architectural concrete, color concrete or any type of special concrete finish product.
• Additional cost due to utility obstructions including any additional work on underground utilities or buried pipes.
• Supply of embedments other than foundation “J” bolts.

 

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation repair work we perform in the Mill Valley area. You can see this work requires skillful experienced foundation contractors and very competent crew. RWR brings you the expertise you need for your important project.

Pipe Pile & Foundation Installation Example Of RWR Competencies

This estimate is based on preliminary architectural and structural drawings. The bid is for the installation of a new reinforced concrete foundation as described below.
Our price includes all labor and material to complete the work as per the itemized Scope of Work below.

Scope of Work
New House Foundation
Mobilization and Supervision
• Mobilize to jobsite. Demobilize.
• Supervision.
• Perform weekly cleanup.

Mass + Foundation Excavation
• Excavate and provide new rough grading (crawl space areas) where new foundations are to be installed for the new footprint of the house as shown on drawings.
• Excavate for the installation of the new house and garage foundation as per plans.
• Stockpile excavated spoils on site within property limits.

Pipe Pile Installation @ Existing House Foundation
• Layout pipe pile locations with general contractor, to be approved by engineering prior to installation.
• Install (27) x a maximum of 20’ deep, 3” diameter hot-dipped galvanized schedule 80 (Fy=36ksi) heavy duty pipe piles, driven into competent bearing strata/practical refusal, defined by a penetration rate of ½” or less per minute for five minutes or as other wise accepted by the Engineer. (See additional footage installation provided below, if needed).
• Fill inside of pipe pile with a neat sand/cement grout mix all the way to the top of the pipe.
• Additional/deductive grouted pipe pile depth cost per foot, respectively.

Shear Plate Assembly Installation @ Existing House Foundation
• Weld a new 7”x 9” x ¼ ”steel pipe pile shear plate/cap assembly on top of each pipe.
• At each pile location, install (4) ½” diameter steel dowels into the existing foundation and connect to new shear plate/cap assembly.

Pipe Pile Installation @ New House Foundation
• Layout pipe pile locations with general contractor, to be approved by engineering prior to installation.
• Install (47) x a maximum of 20’ deep, 3” diameter hot-dipped galvanized schedule 80 (Fy=36ksi) heavy duty pipe piles, driven into competent bearing strata/practical refusal, defined by a penetration rate of ½” or less per minute for five minutes or as other wise accepted by the Engineer. (See additional footage installation provided below, if needed).
• Fill inside of pipe pile with a neat sand/cement grout mix all the way to the top of the pipe.
• Additional/deductive grouted pipe pile depth cost per foot, respectively.

Plate Assembly Installation @ New House Foundation
• Weld a new 7”x 9” x ¼ ”steel pipe pile plate/cap assembly on top of each pipe with (2) ½ “ anchor bolts as per structural detail 1/S3.1.

Drill and Install Piers @ Outdoor Fountain
• Drill and install (8) 18” diameter x 16 ft. deep maximum, reinforced concrete piers. Stockpile all drilling spoils on site. No Off-hauling included
• For additional 18” diameter pier lengths-add per linear ft.
• For 18” diameter pier depth deductions subtract per linear ft.

New House Concrete Foundation + Slab Installation
• Install new house reinforced concrete foundation grade beams, tie beams and stem walls as per layout on structural sheet S2.1 and structural detail assigned. Includes (60) epoxy dowels to attach new to existing foundation @ intersections as per plans.
• As per new first floor framing plan, install approx. 679 square ft. (square footage calculations based on “foundation plan” layout) of 5” thick reinforced concrete slab, with #4 @ 12” o.c., e.w. over 2” of clean sand, 10 mil vapor barrier and 4” of ¾” crushed gravel.
• For the new out door fountain and entry walkway, install approx. 701 square ft. (square footage calculations based on “foundation plan” layout) of 5” thick reinforced concrete slab, with # 4 @ 12” o.c., e.w. over 2” of clean sand, 10 mil vapor barrier and 4” of ¾” crushed gravel.
• Clean up RWR’s related construction debris from site.

Driveway Area
Concrete Footing on Piers
• Excavate for the installation of a new auto court footing approx. 120 ft long x 1.5 ft deep x 1.5 ft wide. Stockpile excavated spoils on site.
• Drill and install (10) 18” diameter x 16 ft. deep maximum, reinforced concrete piers. Stockpile all drilling spoils on site. No Off-hauling included.
• Install reinforced concrete footing as per detail 16/S1.2. CMU wall not included.
Pool House
Foundation Work
• Excavate for the installation of a new pool house foundation as per layout provided on sheet S2.5 and structural detail assigned. Stockpile excavated spoils on site.
• Drill and install (2) 18” diameter x 16 ft. deep maximum, reinforced concrete piers. Stockpile all drilling spoils on site. No Off-hauling included.
• Install new reinforced concrete perimeter and interior footings, perimeter stem walls plus isolated fireplace footing as per dimensions provided on drawings. Pipe piles or piers are not included for the pool house foundation.
• As per new pool house foundation/floor framing plan, install approx. 820 square ft. (square footage calculations based on “foundation plan” layout) of 5” thick reinforced concrete slab, with #4 @ 12” o.c., e.w. over 2” of clean sand, 10 mil vapor barrier and 4” of ¾” crushed gravel.

Foundation Re-leveling
Side
• Re-leveling the affected area (approx. 25 linear ft @ the North & East side of the existing library area) is included, however due to the settlement of the existing foundation and existing conditions the repairs may result in cracked foundations, uneven floor finishes as well as other irregularities. RWR is not including repair of same in this estimate.
• It may not be possible to re-level existing foundation within specified tolerances (½ of an inch maximum) due to existing conditions.
• If bottom of foundation is deeper than 2ft. below existing grade, RWR will charge additional cost for excavation.

Note: re-leveling and attaching the existing foundation to the new pipe piles (see inclusions mentioned above) is included. If structural engineer requires to excavate and install a reinforced concrete haunch under the affected areas there will be additional cost pending structural detail and recommendations.

Notes
• Elevations, secured batter boards, hubs and layout to be provided by General Contractor performing the remainder of the project.
• Pipe Pile installation refusal rate is ¼ to ½ inch depth (or less) per minute for a sustained 5 minute period.

Unit Pricing
• For additional 18” diameter pier lengths-add per linear ft.
• For 18” diameter pier depth deductions subtract per linear ft.
• Additional/deductive grouted pipe pile depth cost per foot, respectively.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Progress payments every two weeks.

Note: This bid assumes RWR will be performing services as a Sub-contractor to a General Contractor. Bid assumes contract will utilize standard RWR contractual provisions. RWR reserves the right to accept or reject General Contractor’s contractual provisions.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Driveway/garage apron or any additional flat work not mentioned above.
• Any work on utilities including buried pipes.
• Removal of soil from site.
• Landscaping/Hardscaping, CMU walls, concrete work as sidewalks, stairs or any other concrete work not mentioned above.
• Waterproofing and drainage.
• Grading, backfilling or re-compaction.
• Demolition hard or soft.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Surveying and Layout.
• Supply of embedments other than foundation bolts.

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of foundation work performed by RWR , demonstrating the level of expertise you want for a job so important to you.

Pipe Pile & Foundation Installation Example Of RWR Competencies

This estimate is based on preliminary architectural and structural drawings. The bid is for the installation of a new reinforced concrete foundation as described below.

Scope of Work

New House Foundation
Mobilization and Supervision
• Mobilize to jobsite. Demobilize.
• Supervision.
• Perform weekly cleanup.

Mass + Foundation Excavation
• Excavate and provide new rough grading (crawl space areas) where new foundations are to be installed for the new footprint of the house as shown on drawings.
• Excavate for the installation of the new house and garage foundation as per plans.
• Stockpile excavated spoils on site within property limits.

Pipe Pile Installation @ Existing House Foundation
• Layout pipe pile locations with general contractor, to be approved by engineering prior to installation.
• Install (27) x a maximum of 20’ deep, 3” diameter hot-dipped galvanized schedule 80 (Fy=36ksi) heavy duty pipe piles, driven into competent bearing strata/practical refusal, defined by a penetration rate of ½” or less per minute for five minutes or as other wise accepted by the Engineer. (See additional footage installation provided below, if needed).
• Fill inside of pipe pile with a neat sand/cement grout mix all the way to the top of the pipe.
• Additional/deductive grouted pipe pile depth cost per foot, respectively.

Shear Plate Assembly Installation @ Existing House Foundation
• Weld a new 7”x 9” x ¼ ”steel pipe pile shear plate/cap assembly on top of each pipe.
• At each pile location, install (4) ½” diameter steel dowels into the existing foundation and connect to new shear plate/cap assembly.

Pipe Pile Installation @ New House Foundation
• Layout pipe pile locations with general contractor, to be approved by engineering prior to installation.
• Install (47) x a maximum of 20’ deep, 3” diameter hot-dipped galvanized schedule 80 (Fy=36ksi) heavy duty pipe piles, driven into competent bearing strata/practical refusal, defined by a penetration rate of ½” or less per minute for five minutes or as other wise accepted by the Engineer. (See additional footage installation provided below, if needed).
• Fill inside of pipe pile with a neat sand/cement grout mix all the way to the top of the pipe.
• Additional/deductive grouted pipe pile depth cost per foot, respectively.

Plate Assembly Installation @ New House Foundation
• Weld a new 7”x 9” x ¼ ”steel pipe pile plate/cap assembly on top of each pipe with (2) ½ “ anchor bolts as per structural detail 1/S3.1.

Drill and Install Piers @ Outdoor Fountain
• Drill and install (8) 18” diameter x 16 ft. deep maximum, reinforced concrete piers. Stockpile all drilling spoils on site. No Off-hauling included
• For additional 18” diameter pier lengths-add per linear ft.
• For 18” diameter pier depth deductions subtract per linear ft.

New House Concrete Foundation + Slab Installation
• Install new house reinforced concrete foundation grade beams, tie beams and stem walls as per layout on structural sheet S2.1 and structural detail assigned. Includes (60) epoxy dowels to attach new to existing foundation @ intersections as per plans.
• As per new first floor framing plan, install approx. 679 square ft. (square footage calculations based on “foundation plan” layout) of 5” thick reinforced concrete slab, with #4 @ 12” o.c., e.w. over 2” of clean sand, 10 mil vapor barrier and 4” of ¾” crushed gravel.
• For the new out door fountain and entry walkway, install approx. 701 square ft. (square footage calculations based on “foundation plan” layout) of 5” thick reinforced concrete slab, with # 4 @ 12” o.c., e.w. over 2” of clean sand, 10 mil vapor barrier and 4” of ¾” crushed gravel.
• Clean up RWR’s related construction debris from site.

Driveway Area
Concrete Footing on Piers
• Excavate for the installation of a new auto court footing approx. 120 ft long x 1.5 ft deep x 1.5 ft wide. Stockpile excavated spoils on site.
• Drill and install (10) 18” diameter x 16 ft. deep maximum, reinforced concrete piers. Stockpile all drilling spoils on site. No Off-hauling included.
• Install reinforced concrete footing as per detail 16/S1.2. CMU wall not included.
Pool House
Foundation Work
• Excavate for the installation of a new pool house foundation as per layout provided on sheet S2.5 and structural detail assigned. Stockpile excavated spoils on site.
• Drill and install (2) 18” diameter x 16 ft. deep maximum, reinforced concrete piers. Stockpile all drilling spoils on site. No Off-hauling included.
• Install new reinforced concrete perimeter and interior footings, perimeter stem walls plus isolated fireplace footing as per dimensions provided on drawings. Pipe piles or piers are not included for the pool house foundation.
• As per new pool house foundation/floor framing plan, install approx. 820 square ft. (square footage calculations based on “foundation plan” layout) of 5” thick reinforced concrete slab, with #4 @ 12” o.c., e.w. over 2” of clean sand, 10 mil vapor barrier and 4” of ¾” crushed gravel.

Foundation Re-leveling
Side
• Re-leveling the affected area (approx. 25 linear ft @ the North & East side of the existing library area) is included, however due to the settlement of the existing foundation and existing conditions the repairs may result in cracked foundations, uneven floor finishes as well as other irregularities. RWR is not including repair of same in this estimate.
• It may not be possible to re-level existing foundation within specified tolerances (½ of an inch maximum) due to existing conditions.
• If bottom of foundation is deeper than 2ft. below existing grade, RWR will charge additional cost for excavation.

Note: re-leveling and attaching the existing foundation to the new pipe piles (see inclusions mentioned above) is included. If structural engineer requires to excavate and install a reinforced concrete haunch under the affected areas there will be additional cost pending structural detail and recommendations.

Notes
• Elevations, secured batter boards, hubs and layout to be provided by General Contractor performing the remainder of the project.
• Pipe Pile installation refusal rate is ¼ to ½ inch depth (or less) per minute for a sustained 5 minute period.

Unit Pricing
• For additional 18” diameter pier lengths-add per linear ft.
• For 18” diameter pier depth deductions subtract per linear ft.
• Additional/deductive grouted pipe pile depth cost per foot, respectively.

Qualifications and Clarifications
• Job is bid as package unless agreement to otherwise
• Includes one mobilization only.
• Prices are subject to RWR obtaining adequate supply of rock, concrete, asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Progress payments every two weeks.

Note: This bid assumes RWR will be performing services as a Sub-contractor to a General Contractor. Bid assumes contract will utilize standard RWR contractual provisions. RWR reserves the right to accept or reject General Contractor’s contractual provisions.

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate). (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Driveway/garage apron or any additional flat work not mentioned above.
• Any work on utilities including buried pipes.
• Removal of soil from site.
• Landscaping/Hardscaping, CMU walls, concrete work as sidewalks, stairs or any other concrete work not mentioned above.
• Waterproofing and drainage.
• Grading, backfilling or re-compaction.
• Demolition hard or soft.
• Excavation of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Surveying and Layout.
• Supply of embedments other than foundation bolts.

 

RWR has done a lot of work in the Mill Valley area, including foundation repairs, retaining walls and drainage repairs. The hilly Mill Valley area, at the foot of Mt Tamalpais gets a lot of rain and moisture, which can cause foundations to become unstable, and retaining walls to fail. It is important to correct these problems with well designed, well engineered plans, that are properly constructed. RWR specializes in this type of construction work in the Mill Valley area, and has great relationships with many engineers and architects working in this area.  If you have a situation you’d like us to look at, please give us a call.

Here’s an example of an extensive foundation repair performed by RWR in the Mill Valley area, just so you can see the level of expertise you want for a job like this:

Drilling, Concrete Piers and Slab

This is an estimate based on unsigned and undated plans provided by contractor. The scope of work includes drilling, installing concrete and steel in pier hole. The price includes all labor and material to complete the work as per the itemized scope of work below.

Scope of Work

Mobilization and Layout
• After existing building has been demolished by others mobilize to jobsite with portable drilling rigs along with other necessary equipment to complete job (See notes below).
• Layout to be completed by others per plans and specifications.
• Daily Cleanup
• Final Cleanup

Piers
• Drill three (3) 18” diameter x 17 ft depth maximum and two (2) 18” diameter x 14 ft depth maximum pier holes with portable drill rig. See drilling conditions and exclusions. Final depths to be determined by soils engineer.
• Install cage per plans and place concrete in hole per plans.
• Includes sono tube as required
• Off haul pier spoils

Slab
• Install approximately 425 sq. ft of 4 inches of light weight concrete over plywood prepared by others per plans. #4 reinforcement @ 18 inches e.w. No waterproofing included.

Qualifications and Clarifications

• Job is bid as package.
• Includes two mobilizations only.
• Prices are subject to obtaining adequate supply of wood, steel, rock, concrete, and asphalt, PVC resins, PVC pipe, fittings at prices quoted at bid time and are good for 30 days.
• Proposal is based on working std 40 hours per week, 5 work days and mutually agreeable schedules.
• Not responsible for survey lines. Survey of property lines must be done by licensed surveyor. Survey points must be provided
• Price is preliminary subject to final plans for construction

Exclusions
• Cost of plans, permits, bonds, testing and inspections.
• Any additional work due to utilities including buried pipes or irrigation pipes unless noted.
• Increased costs of excavation or drilling due to hard rock, caving or underground water. (Hard rock excavation is defined as material that requires the use of pneumatically or hydraulically operated hammers or rams to excavate.) (Hard rock drilling is defined as a penetration rate slower than 1 ft. in 5 minutes).
• Additional cost as a result of unknown obstructions
• Replacement of damaged landscaping, driveway or fence.
• Excavation and off hauling of hazardous materials, underground tanks, or materials unacceptable at dumps.
• Any work related to landscaping, fences or gates except as outlined
• Survey of property lines or layout
• Landscaping or irrigation
• Excludes electrical and plumbing
• Any earth shoring not included
• Any drainage work
• Embedment into concrete including brackets except J bolts
• Permeable concrete

 

Cleaning, repairing or maintaining property drainage pipes can be a bothersome task, especially for busy homeowners in the San Francisco Bay Area, CA. However, preventive measures are strongly recommended to avoid problems down the road. Check out the helpful guide below for a cost-effective and worry-free drainage system.

Knowing the basics

Drainage6The system that collects and drains rainwater and subsurface water from a property is called a drainage system, while sewers collect waste from toilets, sinks and showers.
Drainage system pipes, trenches and catch basins should be kept clean as they are integral parts of property maintenance. Proper and timely maintenance of drainage systems in the San Francisco Bay Area is necessary to protect your home and land against flooding, water infiltration into living areas and under the house, and settlement of foundations. If your home is located at the base of a hill, water can come rushing down the slope in a storm and threaten your property.

In the suburbs, drainage systems outlet to a designated spot on the property or to the street, while in San Francisco, drainage systems are hooked up to the same sewer system that takes away household waste.

During the past decade, the prevailing thinking of how and where to collect rainwater and where to outlet it have changed. Now, the practice of collecting as much rainwater as possible from everywhere and then outleting it in a concentrated flow to the street or a stream is discouraged.
Instead, water should be collected only where it threatens to infiltrate the living areas or crawl space of the house or to cause softening of the ground under the house foundation and subsequent settlement.

The downspouts from the roof should be hooked into a drainage system and the areas around the perimeter of the foundation should either be sloped away from the house or have catch basins connected to a drainage system that collects the water. If the lawn and other areas get soggy, that’s ok, because the water will eventually seep down into the ground.

The drainage system should outlet into a “rain garden”. A rain garden can be an area anywhere on the property where seasonal ponding of water is ok. The water will, over time, seep into the ground, recharging the ground water.
This is now the preferred method for several reasons: it prevents the scouring of creek and streambeds that happens from concentrated loads of rainwater; the street drains are not overloaded; any contaminates that get into the water will seep into and be filtered out by the ground instead of ending up in waterways.

Identifying drainage problems

If you notice water is ponding at catch basins when it rains or downspouts appear to be clogged up or water is building up next to the foundation or in places that that used to drain, you have a problem. If it’s a catch basin, take off the grate and remove any debris and soil from the box. If it’s still not draining, stick a hose down the pipe connected to the box and try to wash the clog out. A downspout may be clogged up at the gutter: get a ladder and check your gutters, particularly where the downspout connects. Track down the reason why water is ponding in new areas near the foundation and try to figure out what has changed. If you have a concrete V-ditch on you property, make sure to keep it cleared of debris and free-flowing. Sometimes it may be necessary to use a plumber’s snake to clear clogged lines.

Leaving it to the experts

Property owners are responsible for keeping their drainage lines and systems cleared and well maintained. But sometimes, drainage issues are beyond the ability of homeowners to take care of themselves. That’s when it’s time to call in an expert. Get a contractor that specializes in drainage systems to come over and evaluate your property. He or she usually has years of experience in identifying drainage problems and installing the proper fixes.

When in need of proper repair or installation of drainage pipes and systems in the San Francisco Bay Area, it’s always a practical approach to employ professionals. Companies like RWR Construction Inc. can help you tackle your drainage problems. RWR can also take on your drilling and other engineering construction needs.